Existing loft
Date: 08/05/07
Views: 1114
|
Existing stair with floor up to get at wiring. Stair will be replaced with a solid oak staircase both ground to first and first
Date: 05/06/07
Views: 713
|
Velux Cabrio windows being installed by John
Date: 12/07/07
Views: 1046
|
Frames in
Date: 12/07/07
Views: 727
|
Units finished - good view up here!
Date: 19/07/07
Views: 805
|
|
Steelwork going in
Date: 19/07/07
Views: 770
|
More steels waiting for mods as problems were found
Date: 19/07/07
Views: 777
|
Velux P10 in the shower room
Date: 31/07/07
Views: 718
|
And complete.
Date: 14/09/07
Views: 706
|
Most of the W truss removed
Date: 10/08/07
Views: 780
|
|
Floor joists going in around the now complete steels
Date: 10/08/07
Views: 821
|
Ready for Glulam ridge beam
Date: 10/08/07
Views: 1075
|
After builder tried to lift Glulam beam up via a ladder!!! A crane was brought in to do the job properly!
Date: 13/09/07
Views: 830
|
Wonder what the neighbours thought?
Date: 13/09/07
Views: 790
|
Pretty big crane
Date: 13/09/07
Views: 792
|
|
First beam
Date: 13/09/07
Views: 713
|
swallowed up
Date: 13/09/07
Views: 794
|
Second beam
Date: 13/09/07
Views: 831
|
Loads of room
Date: 14/09/07
Views: 841
|
Padstones in waiting for beam to go in
Date: 14/09/07
Views: 901
|
|
Air Con Install
Date: 17/09/07
Views: 721
|
Daikin unit
Date: 27/09/07
Views: 723
|
Air Con outlet
Date: 27/09/07
Views: 732
|
Main structural work complete
Date: 27/09/07
Views: 807
|
Light!
Date: 27/09/07
Views: 771
|